BlackLeafwatch the watchmen
Federal energy grant oversight

DOE Overpaid a Terminated Nuclear Reactor Project by $143.5M

Summary

A federal audit found the Department of Energy's Office of Nuclear Energy paid $182.5 million of its $1.36 billion cost-share on a NuScale small reactor project years before the private utilities it needed ever signed up -- and now says the project's company may owe DOE $143.5 million back. The reactor, planned for Idaho National Laboratory, was terminated in 2023 without ever operating; the audit found DOE spent about $183 million on it without achieving its key objective.

By Frontinus · July 20, 2026

The Department of Energy's Office of Nuclear Energy committed $1.36 billion to help build a first-of-a-kind small modular reactor at Idaho National Laboratory. A DOE Inspector General audit released March 24, 2026 found the agency front-loaded its payments so aggressively that it had already paid $182.5 million -- more than four times its actual agreed share -- by the time the project collapsed in 2023 without ever generating a watt of power. says the project's company may now owe $143.5 million back.

The Carbon Free Power Project was supposed to prove that NuScale Power's small modular reactor technology could compete commercially. Instead, auditors found 's Office of Nuclear Energy skipped basic risk evaluation before signing the award, never structured the deal to catch warning signs as they emerged, and paid out taxpayer money years ahead of schedule on a bet that the private sector would eventually catch up. It never did.

A decade-long bet on an unproven reactor

In October 2020, Nuclear Energy finalized a 10-year, $1.36 billion sole-source, non-competitive cost-share award to the Carbon Free Power Project, LLC (CFPP) -- a company wholly owned by Utah Associated Municipal Power Systems (UAMPS), an interlocal agency that supplies wholesale electricity across the Intermountain West. The goal was to build and operate a six-module NuScale small modular reactor plant at Idaho National Laboratory, with total estimated project costs of $8.03 billion. Construction was expected to start in October 2026, with the first power module running by 2029 and the full plant operating by 2030.

None of that happened. In November 2023, CFPP and NuScale mutually agreed to terminate the Project -- years before construction was even due to begin. By then, found, Nuclear Energy had already disbursed approximately $183 million of the $1.36 billion award, and the Project's key objective, an operating, grid-connected reactor meeting its own economic success criteria, was never met.

Total DOE cost-share award
$1.36B
Spent with no result
$183M
Unresolved DOE overpayment
$143.5M

The buyers who never signed up

The Project needed private utilities to sign subscription agreements committing to buy the plant's power before would release the bulk of its funding. OIG found that subscription never came close to target: at the October 2020 award, required 720 megawatts-electric (MWe) of signed capacity, but only 118 MWe was actually subscribed. By February 2024 -- months after the Project was already dead -- the target had been cut to 462 MWe, and actual subscription had crept up to just 120 MWe.

The private buyers never showed up
Megawatts-electric (MWe) of signed subscription, target vs. actual
Target subscription, at award (Oct. 2020)
720
Actual subscribed, at award (Oct. 2020)
118
Target subscription, latest (Feb. 2024)
462
Actual subscribed, latest (Feb. 2024)
120
Source: DOE-OIG Report No. DOE-OIG-26-25, Table 1 (March 2026)
View data as table
OIG found DOE's own merit review never rated the risk that private utilities wouldn't sign up to buy the plant's power -- the single biggest reason the Project was ultimately terminated.
Target subscription, at award (Oct. 2020)720the 100% subscription DOE required before committing
Actual subscribed, at award (Oct. 2020)11816% of target when DOE signed the $1.36B award
Target subscription, latest (Feb. 2024)462target was cut after DOE shrank the plant's capacity
Actual subscribed, latest (Feb. 2024)120barely moved in over 3 years, months after termination

Auditors found Nuclear Energy's own merit review, the process meant to screen applicants before an award, never rated subscription as a risk at all, despite Nuclear Energy officials telling that an entity's ability to obtain the necessary subscription is one of the largest risks to new nuclear deployment today. Once the award was signed, didn't require any interim reporting on subscription progress either -- it didn't plan to formally check the Project's viability until 2026, six years into a project that had already died by 2023.

Paying ahead of schedule -- and ahead of risk

The core mechanism behind the overpayment was what auditors call front-loading: agreed to cover a disproportionate share of costs in the Project's early years, on the expectation that CFPP would cover a higher share later. DOE's Table 2 lays out the math: Nuclear Energy's actual agreed cost-share, calculated against $230.8 million in estimated total project costs at its 16.9% share, came to $39,005,681. But Nuclear Energy had already paid $182,510,163 -- leaving a $143,504,482 gap that says CFPP may now owe the Department back.

DOE paid $143.5 million more than its agreed share
Millions of dollars, Nuclear Energy's cost-share on the terminated reactor project
Agreed cost-share (16.9% of project costs)
39
Actual front-loaded payments
182.5
Source: DOE-OIG Report No. DOE-OIG-26-25, Table 2 (March 2026)
View data as table
The $143.5 million gap between these two bars is what OIG says CFPP may now owe DOE to rebalance the cost-share -- unresolved as the award heads to closeout.
Agreed cost-share (16.9% of project costs)39per the award agreement's cost-share formula
Actual front-loaded payments182.5disbursed to CFPP by the time the Project was terminated

found the front-loading arrangement offered little real protection. Nuclear Energy told auditors it built in safeguards -- primarily the cost-share structure itself, plus the option for CFPP to transfer project assets like studies, licenses, and data to help rebalance the books. But OIG concluded the cost-share can't function as a sufficient safeguard, because if CFPP can't combine cash, in-kind compensation, and asset transfers sufficient to cover the full $143.5 million, the government has no way to recover the money it already paid. Whether the assets CFPP has offered actually have that much value is still being worked out.

Pressure to make a deal happen

also flagged a structural reason may have pushed the Project forward despite the warning signs: Nuclear Energy had a long history of financial support for NuScale itself, separate from the Carbon Free Power award, totaling approximately $586 million in obligations aimed at bringing NuScale's reactor technology to commercial deployment. Auditors concluded that history created inherent pressure to make this deployment succeed, even as there was a documented lack of industry interest in NuScale's technology and stiff competition from other power sources -- and that Nuclear Energy never formally evaluated whether that pressure was biasing its award and risk decisions.

The report notes this isn't 's first time here: 's own prior reports found similar dynamics on the Texas Clean Energy Project, a coal-carbon-capture demonstration also eventually moved to terminate, after accelerating stimulus funds and cutting the developer's required cost-share to keep it afloat -- both of which put more taxpayer money at risk before that project, too, collapsed.

What DOE says, and what happens now

made five recommendations, three aimed at Nuclear Energy's leadership on evaluating risk and enforcing award terms going forward, and two aimed at the contracting officer at 's Idaho Operations Office: determine whether roughly $8,876 in legal costs questioned in a sample review were allowable, and resolve the $143.5 million in unresolved cost-share amounts. Management concurred with four of the five recommendations but pushed back on the audit's overall conclusion, calling it "a flawed and overly critical assessment" of Nuclear Energy's project management, and formally nonconcurred with the recommendation to enforce the award's substantial-involvement oversight terms, arguing those terms were expectations rather than requirements.

rejected that pushback, writing that it reviewed Nuclear Energy's oversight activities against the responsibilities written into its own award and found the agency simply didn't fulfill them -- including never monitoring subscription performance, the risk the report says ultimately killed the Project. Resolution of the questioned $143.5 million and the $8,876 in legal costs is now in the hands of the Idaho Operations Office contracting officer; the report gives no timeline for when that determination will be complete.

  • had paid $182.5 million toward a project that needed $39.0 million from it at this stage -- a $143.5 million overpayment auditors say the terminated project's company may now owe back, with no guarantee the government recovers it.
  • The plant needed private utilities to sign up to buy its power, and they mostly didn't -- signed subscription topped out around 16% of target at the time committed its money, and had reached only about 26% of a reduced target by the time the project was already dead.
  • 's own $586 million history of backing NuScale's technology created pressure to make this deployment work, found, pressure the agency never formally evaluated for bias even as market interest in the technology stayed weak.
  • agrees with most of the findings but disputes the audit's bottom line, formally rejecting the recommendation to enforce its own oversight commitments; the $143.5 million question is now with a contracting officer, with no stated deadline.

Figures are drawn from Office of Inspector General Report No. --26-25 ("Opportunities Exist to Improve the Department of Energy's Oversight of Demonstration and Deployment Projects," released March 24, 2026), read in full including Table 1, Table 2, the Conclusion, and management's complete written response in Appendix 3. The report is a management and cost-allowability audit, not a fraud investigation; it makes no allegation of criminal wrongdoing by , CFPP, NuScale, or UAMPS. The $143.5 million and $8,876 figures are both explicitly unresolved in the report -- questioned them and referred final allowability and cost-share-rebalancing determinations to 's Idaho Operations Office contracting officer, who had not yet resolved either as of the report's release. NuScale continues to operate and pursue other reactor deployment projects separate from the terminated Carbon Free Power Project.

Sources(2) ▾
  • U.S. Department of Energy, Office of Inspector General, Opportunities Exist to Improve the Department of Energy's Oversight of Demonstration and Deployment Projects (2026-03-24)- Report No. --26-25, released March 24, 2026, auditing 's Office of Nuclear Energy's management of the Carbon Free Power Project (the NuScale small modular reactor demonstration at Idaho National Laboratory). Audit conducted June 2024 through August 2025. Fetched directly from energy.gov as a PDF and read page-by-page, including the Highlights summary, Table 1 (subscription tracking), Table 2 (cost-share overpayment calculation), the Conclusion, five Recommendations, and management's full written response in Appendix 3. Every figure in this piece traces to a specific page or table cited in the locator field. energy.gov · original document
  • U.S. Department of Energy, Office of Inspector General, IG Hotline | Department of Energy (2026-07-20)The 's public hotline page, re-fetched this iteration to source the article's call-to-action -- the same office that produced the audit accepts reports of fraud, waste, abuse, or mismanagement in programs and operations, including from contractors, subrecipients, and the general public. energy.gov · original document
Weekly digest: the most-read systems, in brief. Mondays.

Comments

Always open. Logged-in readers can annotate paragraphs in place.

Loading comments…
or log in to comment under your account