FAA skipped Buy American checks on $272.7M in IIJA contracts
Summary
A Transportation Department watchdog reviewed FAA's nine largest airport-modernization contracts funded by the 2021 infrastructure law, worth $405 million combined, and found five missing the contract clauses that make Buy American rules enforceable, plus three using foreign parts under mishandled or stale waivers. FAA disputes the $272.7 million price tag the audit put on the gap. On the one clause where FAA offered its own number, the two sides are about $67.5 million apart.
The clause is the enforcement mechanism
received $25 billion in money between fiscal years 2022 and 2026, $5 billion of it for the facility-and-equipment contracts that are the only funding can spend directly. The Build America, Buy America Act⧉, enacted alongside , was written to push that money toward domestic manufacturers and raises the minimum share of U.S.-made content a project must use in stages -- 55% to 60% in 2022, 60% to 65% in 2024, 65% to 75% by 2029. 's Contracting Officers are supposed to write specific clauses into every -funded contract that hold contractors to those thresholds. In one case, added $71.7 million in funding to a National Airspace System construction contract between August 2023 and May 2024 without ever adding the clause covering Canadian and Mexican construction materials -- and left in place a different, looser domestic-content clause the contract didn't need.
View data as table
| 3.6.4-2 BAA Supplies Clause -- 1 of 6 applicable contracts noncompliant | $48,346,698 |
|---|---|
| 3.6.4-4 USMCA Construction Materials Clause -- 2 of 6 applicable contracts noncompliant | $120,030,081 |
| 3.6.4-6 Balance of Payments Program Clause -- 2 of 2 applicable contracts noncompliant | $67,587,752 |
| 3.18-1 BIL Reporting Requirements Clause -- 3 of 9 applicable contracts noncompliant | $174,512,317 |
The most expensive single gap involved a reporting requirement, not a domestic-content rule. Three contracts added a combined $174.5 million in funds between February 2022 and May 2024 without the clause requiring contractors to itemize any foreign products they used. eventually added the clause to two of the three contracts -- 12 and 22 months late, and only after this audit prompted it. On the third, worth $48.3 million in funds, never added the clause at all. staff told the gaps traced to unclear internal guidance and staff turnover: the Contracting Officers running four of the nine contracts said they lacked the tools to identify which clauses applied, and officials who originally awarded some of the contracts had since left the agency, leaving successors without full institutional memory of what each contract required.
Foreign parts, three different kinds of waiver failure
A waiver is the government's approved exception to Buy American rules -- it lets an agency use a foreign product when domestic supply is unavailable or unreasonably costly, but only after a specific internal review-and-approval process. confirmed used foreign products in three of the nine sampled contracts, together carrying $115.9 million in funds, and found a different failure mode on each: on a $26.5 million power-supply contract, never documented a waiver at all for $2.6 million in foreign-made electrical equipment supporting critical air-traffic communications. On a $48.3 million technical-support contract, a Contracting Officer approved a waiver request for $60,000 in Chinese-made stainless steel fittings without completing the required review template or getting sign-off from legal, 's Acquisition Executive, or the White House's Made in America Office. And on a $41.1 million engine-generator contract first awarded in 2012, kept relying on a Buy American waiver issued in 2014 -- eight years old, never reassessed against 's tighter rules even after funds were added to the contract in 2022.
View data as table
| Total IIJA funds across the nine sampled contracts | $405,179,666 |
|---|---|
| Missing at least one required Buy American clause (5 of 9 contracts) | $272.7 million |
| Not flagged for a missing clause (4 of 9 contracts) | $132,479,666 |
Those same three contracts also miscoded their own paperwork. 's Federal Procurement Data System listed 9 of 10 task orders on the power-supply contract as U.S.-origin even though $2.6 million of foreign purchases sat inside them, and 's own May 2024 report to the White House's Made in America Office claimed 'high confidence' that only $7.7 million -- 0.7% -- of 's $1.18 billion in obligated funds went to foreign products, a figure that excluded the $2.6 million this audit found. never explained the basis for that 'high confidence' claim. On the $48.3 million contract, the Contracting Officer told auditors he'd coded the fittings as domestic because the Chinese-made components made up less than 1% of the contract's total value -- a threshold 's own manual doesn't actually set.
FAA disputes the number -- by how much depends on which clause
's formal written response, included in the report, partially concurred with 's recommendation to fix the missing-clause process but disputed that up to $272.7 million was properly at risk. On one clause, 's argument amounts to a technicality: it says the missing USMCA construction-materials clause actually loosens the domestic-content standard rather than tightening it, so its absence shouldn't count as risk at all. On a second clause, offered a competing number. 's table ties $67,587,752 in funds to two contracts missing the Balance of Payments Program clause, which applies only to work performed outside the U.S. said only one order under one of those contracts was actually performed abroad -- a Bahamas job worth $120,481.78 -- and argued that figure, not the full $67.6 million, is what belongs in the finding. That leaves the two sides about $67.5 million apart on a single clause.
did not back down: it noted the USMCA clause still exposes the U.S. to a risk of breaching its own trade-agreement obligations, and that three of the five noncompliant contracts also had confirmed waiver problems independent of any clause dispute. Both recommendations were closed as 'resolved but open,' with committing to fix its written procedures by November 30, 2026.
- found 5 of the 9 largest contracts funded by the 2021 infrastructure law -- $272.7 million of $405.2 million sampled -- were missing the contract clauses that make Buy American domestic-content rules enforceable.
- 3 of the 9 contracts, carrying $115.9 million in funds, used foreign products under a waiver that was undocumented, improperly approved, or an 8-year-old waiver nobody reassessed.
- 's own procurement data undercounted its foreign spending: a May 2024 report claimed 'high confidence' that just 0.7% of 's $1.18 billion in obligated funds went to foreign products, a figure that excluded a $2.6 million foreign purchase this same audit found.
- disputes 's $272.7 million figure. On the one clause where supplied its own number, the two sides differ by about $67.5 million -- says $120,482 belongs in the finding; 's table says $67,587,752.
- This is 's second flag on the same underlying problem: a 2021 report already found gaps in the agency's Buy American guidance, training, and oversight, before 's stricter rules even took effect.
All six of 's recommendations were accepted in some form and marked 'resolved but open pending completion of planned actions,' with 's own target completion date set for November 30, 2026 -- meaning the fix is a commitment on paper, not yet a completed one, as of this report. Readers with knowledge of contract or procurement fraud, waste, abuse, or mismanagement affecting programs -- including -- can report it to the DOT OIG Hotline, (800) 424-9071, which accepts reports around the clock from employees, contractors, and the public.
Sources(2) ▾
- U.S. Department of Transportation, Office of Inspector General, FAA Did Not Adequately Monitor and Enforce IIJA-Funded Contracts' Compliance With Buy American Requirements (Report No. FI2026025) (2026-04-20) — The self-initiated performance audit of 's award and administration of Infrastructure Investment and Jobs Act ()-funded facility and equipment contracts against Buy American / Build America, Buy America Act (BABA) domestic-content requirements. Source for the $25 billion allocation, the 401-contract/nine-contract sampling methodology, all missing-clause and waiver findings and dollar figures, the FPDS-NG data-quality findings, 's management response and dispute of the dollar figure, and the audit timeline and recommendations status. oig.dot.gov · original document
- U.S. Department of Transportation, Office of Inspector General, FAA Did Not Adequately Monitor and Enforce IIJA-Funded Contracts' Compliance With Buy American Requirements -- report landing page (2026-04-20) — 's own web summary of Report FI2026025, used to corroborate the publish date and top-line figures against the PDF. oig.dot.gov · original document
Comments
Always open. Logged-in readers can annotate paragraphs in place.
DOT's Office of Inspector General⧉ -- the Transportation Department's independent watchdog, whose audit recommendations agencies must formally accept or contest -- reviewed the nine largest contracts into which had funneled money from the 2021 Infrastructure Investment and Jobs Act (). Those nine contracts carried $405,179,666 in funding combined. Five were missing at least one of the contract clauses 's own rules require to make Buy American law enforceable -- a gap valued at approximately $272.7 million. Buy American requirements exist to keep federally funded construction and equipment purchases flowing to U.S. manufacturers rather than foreign suppliers; a missing clause means the government has no contractual hook to make a contractor prove, or a court to enforce, that it complied.