DOE nuclear waste cleanup -- Moab uranium mill tailings

DOE's last uranium cleanup nears $1.16B done. The land is unclaimed

Summary

GAO's July 15, 2026 report on the Moab Mill Site puts DOE's total bill for hauling a Cold War uranium-tailings pile out of Utah's Colorado River watershed at about $1.16 billion -- $970 million of it already spent, entirely by the federal government, with the last of 16-plus million tons due out by mid-2027. It is the last of DOE's original Title I cleanup sites still open, finishing 31 years after every other Title I site closed out in 1998. What GAO's report does not find is a decision: DOE has not determined who will own most of the mill site once the work is done, and DOE's own two offices don't even agree on the year the site changes hands.

By Nero · July 15, 2026

Seventy years after a private mill began processing uranium ore on the bank of the Colorado River, GAO's July 15, 2026 report puts a final number on what it has cost the U.S. government to clean it up: about $1.16 billion, of which has already spent roughly $970 million through fiscal year 2025. The remaining tailings -- about 1 million tons of contaminated material still buried at the site -- are due out by mid-2027, and the Department of Energy's () Office of Environmental Management (EM), the agency office that runs the government's nuclear-cleanup program, expects to finish the job by 2029. Of the 52 sites under the Uranium Mill Tailings Radiation Control Act (UMTRCA), Moab is the last of 's original Title I sites -- the group Congress ordered remediated first -- not yet closed out; finished every other Title I site by 1998.

From a private mill to a federal Superfund-scale job

The Moab Mill Site began in 1956 as a private uranium mill; through 1970 its concentrate went to the U.S. Atomic Energy Commission, 's precursor agency, for the national defense program, before the mill shifted to commercial nuclear-power sales. The private owner shut it down in 1984 and went bankrupt; in 2000 Congress directed to remediate it under UMTRCA Title I. The tailings had been stored in an unlined pond, and the surrounding groundwater is now contaminated with uranium and ammonia that threatens the nearby Colorado River -- the mechanism, not just the fact, of why this is a federal cleanup and not a fenced-off ruin: since 2003, an interim well system has pulled about 1 million pounds of ammonia and over 5,000 pounds of uranium out of that groundwater to keep it from reaching the river.

$970 million spent, $190 million to go
Moab Cleanup Project life cycle cost, in millions of dollars
Spent through FY2025
970
Remaining estimated cost
190
Source: GAO-26-108654
View data as table
DOE has spent about $970 million on the Moab Cleanup Project through fiscal year 2025; GAO estimates about $190 million more to finish, for a total life cycle cost of about $1.16 billion
Spent through FY2025970
Remaining estimated cost190

Why Moab pays nothing local

Most UMTRCA Title I sites split cleanup costs 90/10 with the state where they sit; Moab is exempted from that requirement, and the federal government pays 100 percent, funded through 's Non-Defense Environmental Cleanup account. That single-site $1.16 billion sits inside a much larger number: DOE's FY2025 Agency Financial Report puts 's total environmental cleanup and disposal liability, agency-wide, at about $538.6 billion -- and the same report's independent audit found a material weakness in how EM's environmental-liability estimates are reported, flagged specifically at the Portsmouth/Paducah, Savannah River, Waste Isolation Pilot Plant and Hanford sites. Moab, by contrast, is a single project with an end date can actually price.

16 million tons moved, 1 million left
Uranium mill tailings and contaminated material, in millions of tons, relocated from the Moab Mill Site to the Crescent Junction Disposal Site
Removed as of May 2026
16
Remaining (subsurface material)
1
Source: GAO-26-108654
View data as table
DOE has relocated over 16 million tons of tailings and debris to the Crescent Junction Disposal Site since 2009; about 1 million additional tons of buried material remain, due by mid-2027
Removed as of May 202616
Remaining (subsurface material)1

What's left, and when

The remaining work is itemized and dated: the last roughly 1 million tons of buried tailings move to the Crescent Junction Disposal Site by mid-2027; the groundwater remedy design, about 60 percent finished, needs the Nuclear Regulatory Commission's () concurrence -- UMTRCA's primary regulator for the site -- in 2027, though remediation and monitoring at the site may continue for decades after; site restoration, including realigning the Moab Wash stream, wraps by 2029.

Then comes the handoff: EM expects to transfer the mill site and disposal site to 's Office of Legacy Management (LM), which takes over long-term federal stewardship of closed cleanup sites, by the end of 2029. LM's own most recent Site Management Guide says 2032. The two offices that have to execute the handoff have not reconciled their own paperwork on when it happens.

Moab Cleanup Project total life cycle cost
$1.16B
83% already spent through FY2025 ($970M of $1.16B) -- the federal government pays 100% of it
Tailings and debris moved to Crescent Junction
16M tons
about 1 million tons of buried material still to go, due by mid-2027
Mill site acreage constrained from future use
74%
steep hillsides, easements, rights-of-way or flood zones, per Grand County's 2023 community survey of 179 residents -- and DOE still hasn't decided who owns the land

The land nobody's claimed

DOE intends to keep the disposal site and a limited slice of the mill site permanently, and plans documents point toward transferring most of the mill site's 480 acres to Grand County, Utah, the rural county whose seat is the city of Moab -- but officials told they have not made a final determination. lacks authority under UMTRCA itself to make that transfer; it has two routes. It could use its own Atomic Energy Act authority to grant or sell the land, though officials would not say whether they'd sell or give it away. Or Congress could pass the Moab UMTRA Project Transition Act of 2025 (S.1321/H.R.2681), which would require a free transfer to the county -- introduced in both chambers, but as of May 2026 it had passed neither.

Underneath either path, about 74 percent of the site's acreage is already constrained by steep hillsides, a conservation easement, transportation rights-of-way, or flood hazard, according to Grand County's own 2023 community-vision survey of 179 residents -- the local standard the county itself set for judging what the land can become. found fully followed seven of eight leading practices for engaging those stakeholders, but only partially followed the one about clearly communicating goals: some stakeholders told they remain confused about the land-transfer process itself.

What happens next

EM expects to decide by the end of fiscal year 2026 whether one remaining contaminated property near the site needs remediation, and to finish supplemental-standards paperwork for five adjacent properties by 2028. The final groundwater remedy goes to the in 2027. The last tailings move by mid-2027. Site restoration finishes in 2029 -- the same year EM says the mill and disposal sites transfer to LM, though LM's own planning document says 2032. None of that resolves who owns the land: that depends on a administrative decision that has not been made, or on a congressional bill that has not moved since its 2025 introduction. EM and LM's 2024 memorandum of understanding gives them a 10-year window to sort out the transition -- the same decade in which Grand County expects an answer.

  • 's Moab Mill Site cleanup will cost about $1.16 billion total -- $970 million already spent through FY2025, 100% federally funded -- and is on pace to finish physical work by 2029, closing out the last of 's original Title I UMTRCA sites, 31 years after every other one closed in 1998.
  • The last roughly 1 million tons of buried tailings move to Crescent Junction by mid-2027, after more than 16 million tons already relocated; groundwater contamination that threatens the Colorado River will likely need monitoring for decades past that.
  • has not decided who owns most of the 480-acre mill site once cleanup ends -- and its own Office of Environmental Management and Office of Legacy Management don't agree on whether the handoff between them happens in 2029 or 2032.
  • named two routes to transfer the land to Grand County -- a free conveyance if Congress passes the Moab UMTRA Project Transition Act of 2025, which has sat in Congress since its introduction, or using its own Atomic Energy Act authority to grant or sell the land -- and has not chosen between them.

All figures are from -26-108654, "Nuclear Waste: 's Plans to Complete Cleanup and Transfer of Moab Mill Site," published and publicly released July 15, 2026 -- read in full (12 pages), not just the Highlights summary, which omits Table 1's remaining-work schedule, the 2029-vs-2032 transfer-date discrepancy, and Table 2's stakeholder-engagement scorecard. Dollar and tonnage figures in the charts are 's own rounded totals ($970M/$190M spent/remaining; 16M/1M tons moved/remaining); the $90 million early-phase-spend figure, the ~17 million ton total pile estimate, and the 31-year comparison to the 1998 close-out of 's other Title I sites are this piece's own arithmetic on 's reported figures, not numbers states directly. The $538.6 billion figure is 's FY2025 Agency Financial Report total for environmental cleanup and disposal liability agency-wide (Note 14, FY2025 ending balance) and is not specific to Moab or part of its $1.16 billion; it is cited only for scale. This story pins at the Moab Mill Site, the Crescent Junction Disposal Site 30 miles north where the tailings end up, and headquarters in Washington, where the unresolved land-transfer decision sits (multi-pin doctrine).

Sources(2) ▾
  • U.S. Government Accountability Office, Nuclear Waste: DOE's Plans to Complete Cleanup and Transfer of Moab Mill Site (GAO-26-108654) (2026-07-15)-26-108654, published and publicly released July 15, 2026. A 12-page Q&A report (not just the Highlights page) fetched as a PDF and read in full with pdftotext -layout; it carries the cost ledger (Figure 3), the remaining-work schedule (Table 1), and the stakeholder-engagement scorecard (Table 2) that do not appear in the HTML Highlights summary. Sealed via Artemis on 2026-07-15 (direct gao.gov PDF fetch; Wayback's save endpoint returned HTTP 520 at capture time and carries no prior snapshot of this asset, consistent with the -hosting bot-wall pattern logged elsewhere in Artemis's capture-failure cohort -- the Artemis-sealed copy is the one-click original-document link). gao.gov · original document
  • U.S. Department of Energy, U.S. Department of Energy Agency Financial Report, Fiscal Year 2025 (2025-11-30)'s own audited books: about $538.6 billion in total environmental cleanup and disposal liability agency-wide (Note 14, FY2025 ending balance) -- separate from Moab's own $1.16 billion tailings-cleanup project -- with the independent audit flagging a material weakness in how EM's environmental-liability estimates are reported, specifically at the Portsmouth/Paducah, Savannah River, WIPP, and Hanford sites. Cited here for scale, not as a Moab-specific figure. energy.gov · original document