A federal judge just ruled the EV-charger freeze illegal — $2.74 billion late
Summary
Congress handed states $3.27 billion to build a national EV charging network. In February 2025 the Department of Transportation froze all but the sliver already under contract. A federal judge ruled in January 2026 that it had no legal authority to do that.
Follow the dollar
By the time Emily Biondi, an FHWA associate administrator, sent her letter to state DOTs on February 6, 2025, states had spent three years doing what Congress asked: writing deployment plans, getting them certified, and signing construction contracts. The court's summary judgment order found that $3.27 billion in NEVI funds — the FY2022 through FY2025 slices of the program — had been apportioned and made available to states for obligation. Of that, states had only managed to actually award or obligate $527 million, according to the Congressional Research Service, before the letter arrived. The letter — which the court said "yanked the NEVI Formula Program's cord out of the outlet" — rescinded every state's plan approval and left the remaining $2.74 billion inaccessible, with no date given for when, or whether, it would come back.
View data as table
| Apportioned to states, FY2022–FY2025 | $3,270M | total available for obligation |
|---|---|---|
| Obligated before the freeze | $527M | as of Feb. 6, 2025 |
| Frozen, Feb. 2025 – Jan. 2026 | $2,743M | unlocked by federal court order, Jan. 23, 2026 |
Judge Tana Lin's ruling didn't just criticize the freeze — it found and FHWA had violated the Administrative Procedure Act, vacated the revocations, and issued a permanent injunction barring the agencies from withholding NEVI funds "for any reason not set forth in the or applicable regulations." That $2.74 billion is, per the order, now unlocked. Whether it stays that way is a separate question: as recently as November 24, 2025 — four months after a preliminary injunction had already restored funding rights to 14 of the plaintiff states — FHWA unilaterally deobligated $54.7 million of Washington State's own $55.7 million in FY2022-2025 NEVI funds, citing no legal authority for the move. Judge Lin cited that episode herself as evidence the agency had not shown "a full commitment to appropriate procedure."
Five states, five different-sized holes
The freeze didn't hit every state the same way — it hit whatever each state had already built its plans around. Pennsylvania had $134.9 million riding on its NEVI buildout and lost access to all of it. Vermont had just awarded $9.3 million to eleven fast-charger projects along its busiest corridors when the letter arrived and had to halt the work outright.
View data as table
| Pennsylvania | $134.9M | entire FY22-25 award withheld |
|---|---|---|
| North Carolina | ~$80M | of $86M made available |
| Minnesota | $42.8M | of $53.6M made available |
| Vermont | $15.9M | unobligated FY22-25 balance |
| District of Columbia | $9.6M | of $16.7M five-year award |
The pattern in the court record is consistent across states: money gets approved, states sign contracts and put crews on notice, and then the contracts stall. In the District of Columbia, a conditional grant agreement with Shell to build NEVI-compliant stations collapsed in June 2025 when the freeze made the District's share of funding unreachable. In Vermont, one of the state's own contractors warned officials it might have to lay off employees if the frozen grant meant it couldn't finish a NEVI-funded project it had already staffed up for.
The trade the freeze idled
NEVI money doesn't buy chargers off a shelf — it buys licensed labor. FHWA's NEVI Standards and Requirements final rule requires that every electrician who installs, operates, or maintains NEVI-funded charging equipment hold a certification from the Electric Vehicle Infrastructure Training Program, or complete an equivalent registered-apprenticeship continuing-education track — a federal credentialing layer on top of state electrical licensing, aimed at fixing the reliability problems regulators found in uncertified installations. That requirement draws from a national trade of about 818,700 electrician jobs, per the Bureau of Labor Statistics — the pool every NEVI-certified installer, in every state named above, comes out of. When a state's funding stalls, it isn't an appropriations line that goes idle; it's a signed contract, and the crew hired against it, that does.
The takeaway
- The freeze had no statutory basis, and a court said so. Judge Lin's January 2026 order didn't split the difference — it found the Administrative Procedure Act violation outright and permanently enjoined from repeating it.
- The dollar figures were never in dispute. $3.27 billion apportioned, $527 million obligated, $2.74 billion frozen — the numbers came from the agency's own apportionment records and were unchallenged in the ruling.
- "Restored" isn't "resolved." FHWA was still unilaterally clawing back money — $54.7 million from Washington alone — nine months after a court had already ordered it to stop interfering with state plans.
Figures cover the four fiscal years (FY2022-FY2025) apportioned before the freeze; the FY2026 tranche of the $5 billion program, the program's fifth and final appropriated year under current law, is a separate allocation not included in the frozen totals above.
Sources
- State of Washington et al. v. U.S. Department of Transportation et al., No. 2:25-cv-00848-TL (W.D. Wash.), Order on Motions for Summary Judgment, Jan. 23, 2026 — the ruling itself: the $3.27B/$527M/$2.74B figures, the Biondi Letter timeline, the five state-level frozen amounts, the Washington deobligation episode, and the permanent injunction terms. courthousenews.com
- Congressional Research Service, Status of Federal Implementation of EV Charging Infrastructure (IN12556, updated May 30, 2025) — the $5B/$1B-per-year program structure, the $527 million obligated-before-freeze figure, and the Feb. 6, 2025 freeze timeline. congress.gov
- FHWA, National Electric Vehicle Infrastructure Standards and Requirements, final rule, 88 Fed. Reg. 12724 (Feb. 28, 2023) — the EVITP certification mandate for NEVI installers. federalregister.gov
- U.S. Bureau of Labor Statistics, Occupational Outlook Handbook, Electricians — the 818,700 national electrician employment figure. bls.gov
Comments
Always open. Logged-in readers can annotate paragraphs in place.
The National Electric Vehicle Infrastructure Formula Program was never complicated: the Infrastructure Investment and Jobs Act appropriated $5 billion, split evenly into $1 billion a year for five fiscal years, and told the Federal Highway Administration to hand it to states so they could build fast chargers along the highway system. One week after Transportation Secretary Sean Duffy took office, an FHWA official told every state transportation director that the money was frozen anyway. It took a federal court until January 23, 2026 — eleven and a half months — to rule that the agency had no legal basis to do that.