Two dead reactors are coming back online on $2.52 billion in federal loans
Summary
Palisades and Crane were both headed for the scrapyard. Now $1.52 billion and $1.0 billion in federal loan guarantees are financing the first reactor restarts in U.S. history, reviving upward of 1,200 jobs — while NRC records show $143 million already logged against Palisades' decommissioning trust fund, the account that was supposed to pay for tearing it down.
Follow the loan
Both restarts run on the same federal instrument — a Department of Energy loan guarantee — issued under two different programs eighteen months apart.
View data as table
| Palisades | $1.52B | DOE Loan Programs Office, closed Sept. 2024 |
|---|---|---|
| Crane Clean Energy Center | $1.0B | DOE Loan Programs Office, closed Nov. 2025 |
Holtec International's Palisades project closed a $1.52 billion loan guarantee in September 2024, the first issued under 's Title 17 Energy Infrastructure Reinvestment authority — the 800-megawatt plant had been shut since May 2022 and was partway through decommissioning when Holtec applied to reverse course. Constellation Energy's Crane Clean Energy Center, the 835-megawatt reactor known for 45 years as Three Mile Island Unit 1, closed a $1.0 billion loan in November 2025 under 's newer Energy Dominance Financing Program — the first time the Loan Programs Office finalized a conditional commitment and financial close simultaneously, says, on the strength of Constellation's balance sheet. Neither reactor had generated a watt of power in years. Both are now backed, combined, by $2.52 billion in federal credit.
What was logged against the trust fund meant to bury it
Every reactor operator is required to fund a decommissioning trust fund (DTF) — ratepayer and interest money set aside for exactly one purpose: tearing the plant down. Palisades' DTF is the one under scrutiny. In a Director's Decision issued August 14, 2025 resolving a petition from three environmental groups, the laid out exactly what Holtec had logged against the fund while simultaneously working to restart the plant it was supposed to be dismantling.
View data as table
| Decommissioning expenses logged, 2022–2023 | $143M | NRC DD-25-02 |
|---|---|---|
| Actually withdrawn from the trust fund | $23M | by Dec. 31, 2023 |
| Deferred, to be withdrawn 2040–2041 | $120M | $60M planned each year |
| Found improper by NRC, reimbursed | $57,000 | Severity Level IV noncited violation |
Holtec's own reporting to the showed $143 million in decommissioning-related expenses for 2022 and 2023 combined — but only $23 million had actually been withdrawn from the trust fund by the end of 2023. The remaining $120 million sat as a claim against the fund that Holtec plans to collect later, $60 million in each of 2040 and 2041 — decades after the restart it is now pursuing. Separately, inspections covering the same period found that just over $57,000 of the fund's spending paid for activities that did not qualify as decommissioning under federal regulation — community donations and billing-code errors, the concluded, not a scheme. Holtec reimbursed the money and the agency closed the matter with a Severity Level IV noncited violation, its lowest enforcement tier. Constellation, for its part, has drawn a harder line at Crane: it told regulators it has not and will not tap the Crane DTF to pay for the restart, and in July 2025 asked the to rescind two standing exemptions that would have let it do so without prior notice.
The same machine, counted in jobs
Money aside, both projects are pitched on the same currency: a workforce that a decommissioning schedule was set to shrink to a skeleton crew, now being rebuilt back toward full operating strength.
View data as table
| Palisades | 600 | DOE / Michigan Governor's office |
|---|---|---|
| Crane Clean Energy Center | 600+ | DOE / Constellation Energy |
Palisades is projected to support up to 600 high-quality jobs in Michigan, many held by workers with 20-plus years at the site, at an average salary of $117,845 — with more than 1,000 additional jobs during refueling outages every 18 months. At Crane, Constellation set a hiring target of more than 600 full-time employees before restart, on top of hundreds of contractors drawn mostly from local union halls; 's own loan announcement credits the project with over 600 American jobs. The single hardest constraint at both sites has been the same: new control room operators need an license to run the reactor, and that pipeline — not steel, not the loan — is what is setting the restart date.
The takeaway
- The federal government is underwriting a reversal with no precedent. $2.52 billion in loan guarantees is financing two reactors that had already begun the legal process of permanent shutdown — something no U.S. commercial plant has done before.
- The decommissioning trust fund didn't stay untouched at Palisades. $143 million was logged against it in two years, and while found only $57,000 of that improper, $120 million more is deferred to a withdrawal Holtec now plans for 2040–41 — long after the plant it was meant to bury is scheduled to be running again.
- Crane took the opposite path on the same question. Constellation says it has not touched its decommissioning trust fund for the restart and moved to close the loophole that would have let it, a direct contrast to how the Palisades project financed itself.
Loan figures are the guaranteed amounts at financial close, not funds disbursed to date, which rise with each -approved disbursement. DTF figures cover Holtec's 2022–2023 reporting period only, as reviewed in the 's August 2025 Director's Decision; more recent Palisades DTF activity is not covered here. Job figures are project-level estimates from , state government, and the utilities themselves, not independently audited payroll counts.
Sources
- U.S. Department of Energy, Loan Programs Office — Holtec Palisades project page, the $1.52 billion loan guarantee amount, financial-close date, and job-support figures. energy.gov/edf/holtec-palisades
- U.S. Department of Energy — "Energy Department Closes Loan to Restart Nuclear Power Plant in Pennsylvania" (Nov. 18, 2025), the $1.0 billion Crane Clean Energy Center loan, program name, and jobs figure. energy.gov
- U.S. Nuclear Regulatory Commission — Director's Decision DD-25-02, Holtec Palisades, LLC; Holtec Decommissioning International, LLC; Palisades Nuclear Plant; Petition (issued Aug. 14, 2025; Federal Register 90 FR 40864, published Aug. 21, 2025; ADAMS Accession No. ML25199A096) — the source for all Palisades decommissioning trust fund figures: $143 million logged, $23 million withdrawn, $120 million deferred to 2040–41, and the $57,000 improper-use finding. federalregister.gov
- Office of the Governor of Michigan, Gretchen Whitmer — press release (Sept. 30, 2024) on the Palisades loan guarantee, citing the 600-jobs and $117,845 average-salary figures. michigan.gov
- Constellation Energy — "Constellation to Launch Crane Clean Energy Center, Restoring Jobs and Carbon-Free Power to The Grid," the 600-plus hiring target and union-hall contractor sourcing for Crane. constellationenergy.com
Comments
Always open. Logged-in readers can annotate paragraphs in place.
No commercial nuclear reactor has ever gone from decommissioning back to full power in the United States. Two are attempting it at once. Palisades, on Lake Michigan, and the Crane Clean Energy Center — formerly Three Mile Island Unit 1, on the Susquehanna River — both shut down for good, both began the legal process of permanent closure, and both are now being rebuilt on federal loan guarantees before a single one has finished. The money for the restart and the money set aside to bury the plant are, on paper, two different accounts. In practice, regulators are still sorting out how cleanly that line has held.