Grid coordination died in March 2025. Puerto Rico went dark in April
Summary
GAO told FEMA in 2019 to build a coordination mechanism for Puerto Rico's grid recovery. The coordination team that later existed stopped meeting in March 2025 — DOE cited scheduling conflicts — and weeks later an island-wide blackout hit all 1.4 million customers. GAO's new report orders the mechanism rebuilt, while DOE's own emergency order calls recent investment gains "insignificant."
The documents
Six primary documents, read against each other: GAO-26-107772⧉, the new grid-recovery audit; its 2019 predecessor GAO-20-141⧉; 's two Federal Power Act §202(c) emergency orders of May 16, 2025; 's August 2025 first extension⧉ of both orders — extended four times in all, most recently through August 9, 2026, per the report; and the September 2020 White House statement⧉ announcing $9.6 billion for within almost $13 billion of grants it called "the largest obligations of funding ever awarded" — together exceeded, it noted, only by Katrina and Sandy.
The money
The federal ledger has three columns, and the story lives in the gap between two of them. has obligated $11.1 billion⧉ — legally committed it — but only $2.7 billion has been disbursed; has disbursed $0.6 billion of $2.3 billion; $0.3 billion of $0.9 billion. Across the three agencies, 75 percent of obligated funds have not been paid out; disbursement mostly works as reimbursement, so money moves only after has already spent it. The report also records money moving backward: has reallotted or canceled about $715 million originally meant for community and low-income solar — including up to $350 million in Solar Access Program grants canceled in January 2026 — for needs "yet to be determined." A further $7.6 billion in potential hazard-mitigation benefits sits mostly untouched ($661 million obligated) and expires in September 2027.
View data as table
The people
The grid serves about 1.5 million customers, and its failures reach nearly all of them at once: the April 16, 2025 blackout took down the entire island for almost two days. 's order records the arithmetic of fragility — a single forced outage at Costa Sur Unit 5 shed load for 200,000 customers, and the grid operator's own analysis warns that another baseload failure could mean "up to 135 days and 1,102 hours of load shedding." The cheapest defense is the least done: LUMA reported to 23 vegetation-caused transmission events in twelve months — over 2.2 million customer interruptions, 1.5 billion customer-minutes — and estimates full clearing would prevent more than 80 percent of them. As of February 2026, the federally funded clearing program had covered 400 of 16,000 planned miles.
View data as table
| April 16, 2025 island-wide blackout | 1,400,000 | all 1.4M electric customers, almost 2 days |
|---|---|---|
| Costa Sur Unit 5 forced outage | 200,000 | load-shedding event |
| May 15, 2025 partial blackout | 134,000 |
View data as table
| Cleared | 400 | 2.5% of the plan |
|---|---|---|
| Planned | 16,000 | LUMA: full clearing would cut vegetation outages by 80%+ |
The disagreement between documents
The first disagreement is between and — seven years apart, about the same absence. The 2019 report's Recommendation 3: should establish "a mechanism, or take steps to improve existing mechanisms, for coordination among the multiple local and federal entities involved in grid recovery." 's new report says the agencies addressed its 2019 recommendations. The 2026 report's finding: "a formal mechanism for coordination among all federal and Puerto Rico entities involved in Puerto Rico's grid recovery does not exist." What happened in between is documented in one paragraph on page 46: discontinued the Energy Technical Coordination Team's meetings in March 2025, citing scheduling conflicts, with no future meetings scheduled — and told in December 2025 that meeting "as-needed" was more efficient. Recommendation 5 of the new report orders the mechanism rebuilt, addressed this time to . and agreed with every recommendation.
The second disagreement is between the promise and the emergency order. September 2020: the White House announces $9.6 billion for PREPA⧉ to "repair and replace thousands of miles of transmission and distribution lines," within the largest pair of infrastructure grants in history. May 2025: the Secretary of Energy, invoking emergency authority reserved for wartime and grid crises, finds that "recent investments in the Puerto Rico grid have provided insignificant improvement towards augmenting reliability and security of the grid" — and orders to keep dozens of aging fossil units dispatched and to perform the vegetation management the funded program hadn't delivered. The orders have been renewed repeatedly and now run through August 9, 2026.
What happens next
makes five recommendations — three to on the environmental-review bottleneck (stakeholders said reviews can add months or years per project), two to on documented roles and the coordination mechanism; all five accepted. The hard deadlines are set by other documents: 's emergency orders expire August 9, 2026, in the heart of hurricane season; the $7.6 billion hazard-mitigation window closes in September 2027. As of December 2025, 116 large projects were more than 75 percent complete, so the disbursement curve should finally steepen — but nine years after Maria, the completed-projects column reads nine.
- recommended a grid-recovery coordination mechanism in 2019; discontinued the coordination team that later existed in March 2025; 's 2026 report orders a mechanism rebuilt.
- Weeks after coordination meetings stopped, the April 16, 2025 blackout hit all 1.4 million customers for almost two days.
- 's own emergency order — extended four times, now through August 9, 2026 — calls recent grid investment gains "insignificant." $10.7 billion of $14.3 billion obligated remains undisbursed.
- LUMA ties 1.5 billion customer-minutes of annual outages to vegetation and says full clearing would cut such events by 80%; 400 of 16,000 planned miles are cleared.
Method notes. Obligation figures are 's table 2 ( data as of December 2025; and as of February 2026); totals may not sum due to rounding, and an obligation is a legal commitment while a disbursement is money paid out — notes disbursement to typically works as reimbursement for completed work. Vegetation-event and customer-interruption figures are LUMA's reporting to , quoted in Order 202-25-2. The 2019 recommendations were closed as addressed; the sequence from the March 2025 discontinuation to the April 2025 blackout is chronological, from the documents' own dates — the report does not assert causation, and neither does this piece. BlackLeaf's July 9 piece on this system covered the review-staffing bottleneck from the same report; this piece is built on five additional primary documents.
Sources(6) ▾
- U.S. Government Accountability Office, Puerto Rico Grid Recovery: Limited Progress Toward Stability and Opportunities Exist to Improve Federal Assistance (GAO-26-107772) (2026-06-30) — The new report (cover-dated June 2026, released publicly in early July 2026 via the House Natural Resources Committee). Source of the obligation/disbursement table, the nine-completed-projects count, the 400-of-16,000-mile vegetation figure, the solar reallotments, the discontinued coordination team, and the five recommendations. gao.gov · original document
- U.S. Government Accountability Office, Puerto Rico Electricity Grid Recovery: Better Information and Enhanced Coordination Is Needed to Address Challenges (GAO-20-141) (2019-10-08) — The 2019 predecessor. Its Recommendation 3 — a coordination mechanism among the multiple local and federal entities — is the seven-year-old ancestor of 2026's Recommendation 5. Also documents that as of July 2019 neither nor had funded a single long-term grid recovery project. gao.gov · original document
- U.S. Department of Energy, DOE Emergency Order No. 202-25-1 (Federal Power Act §202(c)) — PREPA Generation (2025-05-16) — The Secretary of Energy's emergency determination: the April 16, 2025 island-wide blackout hit all 1.4 million electric customers; a May 15 partial blackout hit 134,000; 'Recent investments in the Puerto Rico grid have provided insignificant improvement'; a further baseload failure could mean up to 135 days and 1,102 hours of load shedding. energy.gov · original document
- U.S. Department of Energy, DOE Emergency Order No. 202-25-2 (Federal Power Act §202(c)) — PREPA Transmission / Vegetation (2025-05-16) — Orders to perform vegetation management on specified transmission lines. Documents LUMA's report to : 23 vegetation-related transmission events from May 2024 to April 2025, over 2.2 million customer interruptions and 1.5 billion customer-minutes of interruption; full clearing would avoid over 80 percent of events. energy.gov · original document
- U.S. Department of Energy, Energy Department Extends Emergency Order to Strengthen Grid Security in Puerto Rico (first extension) (2025-08-14) — 's August 2025 announcement of the FIRST extension of both emergency orders, through November 12, 2025 — evidence the emergency regime persisted past its initial term. Per -26-107772 (footnotes 50 and 67), extended the orders four times, most recently in May 2026 as Orders 202-25-1D/2D through August 9, 2026. energy.gov · original document
- The White House (archived), Statement from the Press Secretary on the Largest FEMA Infrastructure Grants Being Awarded to Puerto Rico (2020-09-18) — The promise ledger: $9.6 billion for to 'repair and replace thousands of miles of transmission and distribution lines' — announced as the largest obligations of funding ever awarded by , exceeded only by Katrina and Sandy in total Public Assistance. trumpwhitehouse.archives.gov · original document
Comments
Always open. Logged-in readers can annotate paragraphs in place.
In October 2019, told to establish a coordination mechanism⧉ among the many federal and Puerto Rico entities rebuilding the island's grid. In June 2026, 's new report⧉ makes the same demand again — because the coordination body that later existed — the Energy Technical Coordination Team — was discontinued by in March 2025 over "scheduling conflicts." Weeks later, on April 16, 2025, an island-wide blackout reached all 1.4 million electric customers for almost two days. The Secretary of Energy responded with emergency orders — still in force today — whose first page finds that "recent investments in the Puerto Rico grid have provided insignificant improvement." Those investments: $14.3 billion obligated since 2017, of which three-quarters has never been disbursed.