BlackLeafwatch the watchmen
Postal Service

USPS's new electric vans spent up to 14 months parked in holding lots

Summary

In March 2022 the Postal Service's own purchasing model, run at a lowball $2.71-a-gallon gas price, recommended an order that was 80 percent gas-powered -- and GAO found that adding just $1 to that price would have flipped the model to nearly 90 percent electric. Eight months later, prodded by a $3 billion federal appropriation, USPS reversed course and ordered thousands of electric E-Transits instead. By June 2025 it had delivered 7,465 of the 9,250 it promised -- but had nowhere to plug in 6,036 of them, some parked at holding lots for as long as 14 months, while a second round of postponed savings, worth $78 million, piled onto the $77 million already lost to the prior year's production shortfall.

By Locusta · July 12, 2026

The Postal Service's own purchasing model said the math was close: raise the price of gas by a dollar and the model would recommend electric vehicles for nearly nine of every ten routes instead of one in ten. controlled that variable. It picked $2.71 a gallon -- a price gas hadn't held for months -- and used it to justify an order that was 80 percent gas trucks in March 2022. Then, pushed by a $3 billion federal appropriation, reversed field and ordered thousands of electric vans anyway. By June 2025 it had built more than it could plug in: 6,036 electric delivery vans sitting in parking lots, one of them for 14 months, while two consecutive inspector general audits tallied a combined $155 million in savings the delays have cost.

A gas price too convenient to check

's contract with Oshkosh Defense let it order 50,000 to 165,000 next-generation delivery vehicles with a choice of gas or electric powertrains. For its March 2022 order -- 50,000 vehicles, 39,981 gas and 10,019 electric, worth $2.98 billion -- ran its cost model on an assumed gas price of $2.71 a gallon. GAO found that never disclosed the methodology behind that number, and that it excluded a price run-up that had already happened: the national average had climbed from $3.19 in October 2021 to $4.24 by March 2022, per EIA data cited in the same report. then tested what a more current price would have done to the model's own output -- and found that raising the assumed gas price by just $1 flipped the recommendation from about 10 percent electric to almost 90 percent.

Raise the gas price 50 cents, the model flips electric
Electric-vehicle share of USPS's purchasing-model recommendation for the 2022 order, by test gas price
Gas priced $0.50 below GAO's test midpoint
10%
Gas priced at GAO's test midpoint
57%
Gas priced $0.50 above the midpoint
86%
Source: GAO-23-106677, Figure 1 (Apr. 2023)
View data as table
Electric-vehicle share of recommended order, by test gas price
Gas priced $0.50 below GAO's test midpoint10%USPS's chosen $2.71 sat near this end of the range
Gas priced at GAO's test midpoint57%
Gas priced $0.50 above the midpoint86%near where gas actually reached by March 2022
E-Transits sitting idle in holding lots
6,036
as of June 30, 2025 -- 81% of plan delivered, none of it deployed
Longest one has been parked
14 months
Atlanta (GA) and Santa Clarita (CA) holding lots
Postponed savings, two audits running
$155M
$77M (FY24-25) + $78M (FY25-26)

The pivot nobody built docks for

Money changed the calculus that transparency hadn't. In August 2022, the Inflation Reduction Act appropriated $3 billion to for zero-emission vehicles and charging infrastructure. By December 2022, announced it would flip its order to a minimum of 75 percent electric out of 60,000 next-generation vehicles -- the opposite mix from what it had told Congress the numbers supported nine months earlier. That reversal sat inside a much larger plan: 106,480 new delivery vehicles between fiscal 2023 and 2028, a nearly $10 billion investment including the $3 billion in federal funds. The purpose-built electric van, the Next Generation Delivery Vehicle, missed its own numbers early: 's inspector general reported that the original plan called for more than 3,050 NGDVs delivered by June 2024; the plan current as of that October 2024 audit called for 28. The estimated the resulting delays would postpone more than $77 million in savings between fiscal 2024 and 2025.

Delivered faster than the plugs could keep up

The vehicle that did ship on schedule created a different problem. 's plan called for 9,250 E-Transits -- a commercial, left-hand-drive electric van needing no custom tooling. By June 2025, had acquired 7,465 of them, 81 percent of the plan and only 1,785 behind its own April 2024 schedule -- the opposite failure mode from the NGDV. But delivery units didn't have the charging infrastructure or compatible routes to put them to work. 's fix was to park them: as of June 30, 2025, 6,036 E-Transits sat at eight holding lots nationwide, some as long as 14 months. The inspector general estimated this postponed more than $78 million in savings between fiscal 2025 and 2026 -- on top of the $77 million already lost to the prior year's production shortfall.

Ordered, delivered, undeployed
USPS E-Transit acquisition status, as of June 2025
Planned by the April 2024 schedule
9,250
Actually acquired by June 2025
7,465
Sitting unused in holding lots
6,036
Source: USPS OIG Report 25-063-R25 (Sept. 2025), Tables 1-2
View data as table
Planned by the April 2024 schedule9,250
Actually acquired by June 20257,46581% of plan
Sitting unused in holding lots6,036as long as 14 months
Where the idle vans are parked
E-Transits stored by holding lot, June 30, 2025
Atlanta (GA) CTHO
3,114
Santa Clarita (CA) VMF
603
New Jersey NDC
442
Norfolk (VA) VMF
614
Carol Stream (IL) VMF
325
Seattle (WA) VMF
497
Lehigh Valley (PA) VMF
343
Harrisburg (PA) VMF
98
Source: USPS OIG Report 25-063-R25, Table 2
View data as table
Vehicles held vs. longest tenure, by facility
Atlanta (GA) CTHO3,11414 months
Santa Clarita (CA) VMF60314 months
New Jersey NDC44213 months
Norfolk (VA) VMF61411 months
Carol Stream (IL) VMF32511 months
Seattle (WA) VMF4977 months
Lehigh Valley (PA) VMF3434 months
Harrisburg (PA) VMF983 months
Total6,036across 8 holding lots

Paying twice for the parking

Storing a van is not free. hired garage assistants at three holding lots; it also contracted third-party security at one holding lot. At one lot, staff paid a local contractor to charge more than 180 E-Transits at a public location instead of using the free chargers already installed at Postal Service facilities, citing manpower shortages and charging restrictions at the vehicle maintenance facility. The inspector general put a number on that decision: $37,058 in questioned costs between February and April 2025 alone. The same audit found E-Transit batteries charged to 90 and 100 percent during extended storage -- above both 's own 70 percent guideline and the supplier's roughly 50 percent recommendation for vehicles held longer than 30 days -- a practice that risks voiding the vehicles' limited warranty before they ever deliver a package.

Two straight audits, two years of savings pushed back
USPS OIG-estimated postponed fleet-modernization savings, by report
FY2024-2025 (NGDV/BEV production delays)
77
FY2025-2026 (E-Transit holding-lot delays)
78
Source: USPS OIG Reports 24-051-R25 (Oct. 2024) and 25-063-R25 (Sept. 2025)
View data as table
FY2024-2025 (NGDV/BEV production delays)77
FY2025-2026 (E-Transit holding-lot delays)78

The takeaway

  • 's own model said the gas price was the swing factor, then picked the number. A $1 change in the assumed price of gas -- well within the range gas had already moved through -- would have flipped the March 2022 order from mostly gas to nearly 90 percent electric.
  • The correction came from Congress's money, not a corrected model. A $3 billion Inflation Reduction Act appropriation, not a fixed cost estimate, is what itself cited for accelerating electric purchases by nearly 560 percent.
  • Buying the right vehicle isn't the same as being able to use it. delivered E-Transits ahead of the charging infrastructure needed to plug them in, and two consecutive inspector general audits have now tallied a combined $155 million in savings lost to acquisition and deployment delays.

agreed with five of the inspector general's six E-Transit recommendations in the September 2025 report and disagreed with one. It disputed the 's characterization of "mixed results," said it had moved more than 1,000 E-Transits into daily operation after commissioning additional charging infrastructure, and disagreed that battery charging or local contracting practices were inconsistent. All figures are from the two audit reports and the April 2023 report cited throughout; the $155 million combined-savings figure sums two separate estimates covering different (if adjacent) delay periods, not a single audited total.

Sources(3) ▾
  • U.S. Government Accountability Office, U.S. Postal Service: Action Needed to Improve Credibility of Cost Assumptions for Next Generation Delivery Vehicles (2023-04-20)the $2.71 gas-price assumption, the undisclosed $3.19-to-$4.24 price jump it excluded, the sensitivity analysis showing a $1 gas-price swing flips the model's recommendation between about 10% and 90% electric, and the March 2022 initial order mix and Inflation Reduction Act appropriation gao.gov · original document
  • United States Postal Service Office of Inspector General, Fleet Modernization: Delivery Vehicle Acquisition Status (Report Number 24-051-R25) (2024-10-03)the 106,480-vehicle, nearly-$10-billion fleet modernization plan; the Next Generation Delivery Vehicle shortfall (28 delivered vs. a plan of over 3,050); and the $77 million in postponed FY2024-2025 savings uspsoig.gov · original document
  • United States Postal Service Office of Inspector General, Fleet Modernization: E-Transit Vehicle Acquisition Update (Report Number 25-063-R25) (2025-09-16)the E-Transit acquisition schedule (Table 1) and eight-holding-lot storage table (Table 2), the $78 million in postponed FY2025-2026 savings, the 560% BEV order increase, the $37,058 in questioned local-charging costs, and the battery-storage/warranty-risk finding uspsoig.gov · original document
Weekly digest: the most-read systems, in brief. Mondays.

Comments

Always open. Logged-in readers can annotate paragraphs in place.

Loading comments…
or log in to comment under your account